(Solved): The project team has performed an earned value analysis on its project and has calculated that the S ...



The project team has performed an earned value analysis on its project and has calculated that the SPI is 0.30 and the CPI is 1.0. The team is trying to determine how efficient they will need to be with the remaining resources to complete the project on budget. Which of the following statements best describes the current state of the project? Question 1Select one: a. The project is on schedule and on budget. b. The project is behind schedule and on budget. c. The project is on schedule and over budget. d. The project is behind schedule and under budget.